Thursday, September 5, 2013

The new IEC 61439: better or worse than its predecessor 60439?

Improvements in IEC 61439 series compared to IEC 60439 series.

The new document structure:

Readability of the IEC 61439 has been improved compared to the IEC 60439 by implementing the

new structure of the clauses:

a) Clauses for normative reference and definitions are separated;

b) Newly introduced in clause 4 is a table with all the typical units for LV systems;

c) Also n important change is the separation the constructional requirements (clause 8) and the

performance (electrical) requirements (clause 9);

d) Design verification in clause 10 has been detailed, with more guidance and rules for the

various verification methods;

e) Routine verification in clause 11 has been separated from the design verification.

These improvements acknowledge that the assembly manufacturer/designer focuses on the

constructional and performance requirements and less bothers with de design verification which is for

the laboratories to address.

 

Introduction of designated design verification methods

A significant change in the new LV Assembly standard is the introduction of three methods of design

verification to replace TTA and PTTA (Type Tested Assembly and Partially Type Tested Assembly).

Where TTA in principle required complete testing of all assemblies or modular LV assembly systems,

the new standard acknowledges that assemblies or modular LV assembly systems may be

manufactured in various similar arrangements that can be sorted in variants. IEC 61439 requires

design verification of the critical variants only. To sort the critical variants a number of rules are

provided in order to avoid superfluous testing.

Where PTTA allowed calculation (that was applied to the discretion of the assembly manufacturer) for

some verifications the new standard introduces concrete rules for this method. In essence these rules

limit the loading of parts and conductors to values that are considered safe in case no true test is

performed. Note that verification of temperature rise is limited to assemblies with a total current of

1600 A, above that one is obliged to test with current.

The new standard allows the manufacturer to combine the different methods for verification as long as

it is indicated in the test report which method was used for the individual design verification.

Better or worse?

In general the new standard is better, due to the new structure, the new introduced clear methods of

verification and abandoning the vague terms TTA and PTTA.

It is worse where it bothers laboratories to verify the constructional requirements regarding the

incorporation of switching devices and components, wiring and terminals, information that is not

always easy to come by. Probably only half of the verifications in this area are useful. Many of the

items are subject to an agreement between user and manufacturer and therefore may vary for each

one-off assembly.

 

Written for Eaton MCC Forum

Bas Bouman

Applications and Standards LV Systems

Eaton Electric B.V.

Hengelo The Netherlands.

12 May 2010

Tuesday, September 3, 2013

Friday, August 30, 2013

Schneider Electric - Low voltage switchboards Quality inspection guide

 

1. Introduction to quality inspection

1.1. Justification for quality inspection 4

1.2. Quality inspection function 5

1.3. Quality inspection responsibility 5

1.4. Quality inspector’s profile 5

1.5. Necessary documents 5

1.6. Required human resources 5

1.7. Inspection diagram 6

2. Incoming delivery inspection

2.1. Justification for the incoming inspection 8

2.2. Procedures 9

3. In-process inspection

3.1. Inspection during manufacturing 10

3.2. Justification for the inspection

during the manufacturing stage 10

3.3. Process 11

3.4. Means 11

4. Final inspection

4.1. Final inspection process 12

4.2. Operating rules 13

4.3. Non-conformity treatment process 14

4.4. Conformity declaration 15

5. Summary of tasks after final inspection stage

5.1. Customer acceptance before installation 16

5.2. Installation 16

5.3. Commissioning 16

 

DOWNLOAD :

 

http://www2.schneider-electric.com/documents/panelbuilders/en/shared/project-management/DESWED101005EN-web.pdf

Wednesday, August 28, 2013

IK Shock-Protection Rate

IK Shock-Protection Rate

IK-Class 

IK 00 No Shock-Protection 

IK 01 Resistance against impacts with an energy up to 0,150 J

IK 02 Resistance against impacts with an energy up to 0,200 J

IK 03 Resistance against impacts with an energy up to 0,350 J

IK 04 Resistance against impacts with an energy up to 0,500 J

IK 05 Resistance against impacts with an energy up to 0,700 J

IK 06 Resistance against impacts with an energy up to 1,00 J

IK 07 Resistance against impacts with an energy up to 2,00 J

IK 08 Resistance against impacts with an energy up to 5,00 J

IK 09 Resistance against impacts with an energy up to 10,00 J

IK 10 Resistance against impacts with an energy up to 20,00 J

Thursday, August 22, 2013

Friday, August 16, 2013

Thursday, August 15, 2013

Overview of the main verification changes (IEC 61439 vs IEC 60439)

> Design verification

 

·         Increased requirements for insulating materials and transient overvoltages withstand tests.

·         Temperature rise verification:

ü  Verification by test of each functional unit loaded alone with its rated current

ü  Clear methods for the selection of representative samples of an Assembly system to be tested

ü  Test done in 4 steps: individual functional units, main and distribution busbars, and complete

Assembly

ü  Heating resistors only allowed to simulate circuits adjacent to a circuit under test

ü  Possible verification by comparison with a tested design under strict conditions, including derating

ü  Exemption of test (calculation) only allowed up to 1600 A instead of 3150 A under strict conditions,

including a 20% derating.

·         Possible short-cricuit withstand verification by comparison with a tested design under strict

condition

·         200 operating cycles instead of 50 for locking, interlocking and withdrawable parts

·         Lifting test (from IEC 62208)

·         Corrosion resistance test for metallic parts (from IEC 62208).

 

> Routine verification

 

ü  More detailed list of the verifications

ü  More severe requirements for clearances

SCHNEIDER ELECTRIC

Wednesday, August 14, 2013

Tuesday, August 13, 2013

ENCLOSURE CERTIFICATES & APPROVALS

NEMA

National Electrical Manufacturers’ Association

2101 L Street Northwest, Washington, DC 20037

NEMA Standards Publication No. 250

Enclosures for Electrical Equipment (1000 Volts Maximum)

NEMA Standards Publication No. ICS6

Enclosures for Industrial Controls and Systems

 

UL

Underwriters' Laboratories Inc.

333 Pfingsten Road, Northbrook, Il 60062

UL 50 Cabinets and Boxes

UL 508 Industrial Control Equipment

UL 870 Wireway, Auxiliary Gutter, and Associated fittings.

 

CSA

Canadian Standards Association

178 Rexdale Boulevard, Rexdale, Toronto, Ontario Canada

M9W 1R3

CSA Standard C22.2, No. 14 Industrial Control Equipment

for Use in Ordinary (Non-Hazardous) Locations

CSA Standard C22.2, No. 40 Cutout, Junction,

and Pull Boxes

CSA Standard C22.2, No. 94-M91 Special Purpose

Enclosures

 

JIC

Joint Industry Counsel

7901 Westpark Drive, McLean, VA 22101

EMP-1 Electrical Standards for Mass Production Equipment

EGP-1 Electrical Standards for General Purpose

Machine Tools

 

IEC

International Electrotechnical Commission

3 Rue de Varemb, CH-1211

Geneva 20, Switzerland

IEC 529 Classification of Degrees of Protection

Provided by Enclosures

 

ANSI

American National Standards Institute

1430 Broadway

New York, NY 10018

ANSI Z55.1-1967 Gray Finishes for Industrial

Apparatus and Equipment

 

EEMAC

Electrical/Electronic Manufacturers Association of Canada

10 Carlson Court

Suite 500

Rexdale (Toronto), Ontario Canada M9W 6L2

 

TUV

TUV Rheinland

Glenview, IL

Newtown, CT

San Ramon, CA

 

VDE

Institute of German Electronics Engineers

Merianstrasse 28

D-6050 Offenbach, Germany

 

EIA

Electronic Industries Association

2001 Eye Street Northwest

Washington, DC 20006

EIA RS-310-D Racks, Panels, and Associated Equipment

 

NFPA

National Fire Protection Association

Batterymarch Park

Quincy, MA 02269

NFPA 70 National Electrical Code

 

More Info :

http://www.galco.com